Project Overview:
Client: Commercial Office
Location: East Midlands Airport
Industry: Commercial Office
System Size: 135.64Wp + 224kW Battery Storage
Carbon Savings: 23,330kg of CO2 / Year
Annual Energy Generation: 114,851kWh


Background:
Our client asked us to provide a tender price for a solar project. They were focused on reducing cost and reducing their carbon footprint.
• Challenges: The office consumed large amounts of electricity and the entire roof would be needed to mitigate costs.
• Objectives: Reduce annual energy costs and the reliance on the grid whilst maintaining a commercially viable solution.
Solution Provided:
• System Design: A roof mount system utilising HT 495W panels. We also looked at a solar car port and offered both designs.
• Installation Process: Installation of roof mount array The install was then 2 weeks on site.
• Technology Used: 2 No. FoxESS T20-G3 Inverters, 1 no. FoxESS G Max 225kWh battery.. HT60-18X(ND)-F-495 Solar Panels